| Project Completion Certificate (Ground Water) | |||
|---|---|---|---|
| Scheme ID: 20078457 | Name of Scheme: NIHORI | No. of Villages: 1 | No. of Habitation Covered: 1 |
| Total Population Covered: 1278 | Base Year: 2023 | Intermediate Year: 2038 | Design Year: 2053 |
| Date of Completion (As per Contract): 31-Dec-2024 | Actual Date of Completion (Capex): 29-Sep-2024 | ||
| Tubewells | |||||
|---|---|---|---|---|---|
| Sno. | Description | Depth of Strainer (m) / Depth of Plain Pipe (m) | Location | Latitude | Longitude |
| 1 | Tubewell | 17.6 Mtr / 102.36 Mtr | NIHORI | 29.157368 | 77.783726 |
| Pumps | |||||
|---|---|---|---|---|---|
| Sno. | Type of Pump | Discharge (M³) / Head(Mtr.) | Location | Latitude | Longitude |
| 1 | Submersible | 250 LPM / 46 Mtr | NIHORI | 29.157368 | 77.783726 |
| OHT's | |||||
|---|---|---|---|---|---|
| Sno. | Structure | Capacity (In KL) / Staging Ht.(Mtr.) | Location | Latitude | Longitude |
| 1 | Direct Pumping Schemes | Direct Pumping Schemes | NIHORI | 29.157368 | 77.783726 |
| Clear Water Rising Main | ||||
|---|---|---|---|---|
| Sno. | Pipe Type / Material | Dia (In mm.) | Length (In KM.) | Remarks |
| 1 | DI | 100 | 0.004 | |
| Distribution Network | ||||
|---|---|---|---|---|
| Sno. | Pipe Type / Material | Dia (In mm.) | Length (In KM.) | Remarks |
| 1 | HDPE | 63 | 1.328 | |
| 2 | HDPE | 90 | 0.804 | |
| 3 | HDPE | 110 | 0.222 | |
| HSC Connection | |
|---|---|
| Sno. | Total Nos. |
| 1 | 282 |