| Project Completion Certificate (Ground Water) | |||
|---|---|---|---|
| Scheme ID: 20080869 | Name of Scheme: AMARHAT VILLAGE WATER SUPPLY SCHEME | No. of Villages: 1 | No. of Habitation Covered: 4 |
| Total Population Covered: 2069 | Base Year: 2022 | Intermediate Year: 2037 | Design Year: 2052 |
| Date of Completion (As per Contract): 12-Aug-2024 | Actual Date of Completion (Capex): 10-Mar-2024 | ||
| Tubewells | |||||
|---|---|---|---|---|---|
| Sno. | Description | Depth of Strainer (m) / Depth of Plain Pipe (m) | Location | Latitude | Longitude |
| 1 | Housing Plain Pipe 200 mm | 0 | Amarahat | 26.006185 | 83.482407 |
| 2 | Plain Pipe 150 mm | 41.78 | Amarahat | 26.006185 | 83.482407 |
| 3 | Slotted Pipe 150mm | 51.51 | Amarahat | 26.006185 | 83.482407 |
| 4 | Plain Pipe 150mm | 54.51 | Amarahat | 26.006185 | 83.482407 |
| 5 | Slotted Pipe 150mm | 72.53 | Amarahat | 26.006185 | 83.482407 |
| 6 | Plain Pipe 150mm | 84.55 | Amarahat | 26.006185 | 83.482407 |
| 7 | Slotted Pipe 150mm | 94 | Amarahat | 26.006185 | 83.482407 |
| 8 | Plain Pipe 150mm | 100.01 | Amarahat | 26.006185 | 83.482407 |
| Pumps | |||||
|---|---|---|---|---|---|
| Sno. | Type of Pump | Discharge (M³) / Head(Mtr.) | Location | Latitude | Longitude |
| 1 | 10 HP Pump | 450/46 | Amarahat | 26.006185 | 83.482407 |
| OHT's | |||||
|---|---|---|---|---|---|
| Sno. | Structure | Capacity (In KL) / Staging Ht.(Mtr.) | Location | Latitude | Longitude |
| 1 | Zin Alum Tank | 150/12 | Amarahat | 26.006183 | 83.482406 |
| Clear Water Rising Main | ||||
|---|---|---|---|---|
| Sno. | Pipe Type / Material | Dia (In mm.) | Length (In KM.) | Remarks |
| 1 | DI K-7 | 100 | 0.02 | |
| Distribution Network | ||||
|---|---|---|---|---|
| Sno. | Pipe Type / Material | Dia (In mm.) | Length (In KM.) | Remarks |
| 1 | HDPE Pipe | 63 | 7.762 | |
| 2 | HDPE Pipe | 75 | 0.44 | |
| 3 | HDPE Pipe | 90 | 0.41 | |
| 4 | HDPE Pipe | 110 | 0.34 | |
| HSC Connection | |
|---|---|
| Sno. | Total Nos. |
| 1 | 250 |