Project Completion Certificate (Ground Water)
Scheme ID: 20082592 Name of Scheme: KHATA SAKOTI No. of Villages: 2 No. of Habitation Covered: 2
Total Population Covered: 6207 Base Year: 2023 Intermediate Year: 2038 Design Year: 2053
Date of Completion (As per Contract): 31-Dec-2024 Actual Date of Completion (Capex): 25-Sep-2024
Tubewells
Sno. Description Depth of Strainer (m) / Depth of Plain Pipe (m) Location Latitude Longitude
1 Tubewell 50.66 Mtr / 94.27 Mtr KHATA - SAKOTI 29.172713 77.871537
Pumps
Sno. Type of Pump Discharge (M³) / Head(Mtr.) Location Latitude Longitude
1 Submersible 1250 LPM / 56 Mtr KHATA - SAKOTI 29.172713 77.871537
OHT's
Sno. Structure Capacity (In KL) / Staging Ht.(Mtr.) Location Latitude Longitude
1 OHT 375 Kl / 18 M KHATA - SAKOTI 29.172713 77.871537
Clear Water Rising Main
Sno. Pipe Type / Material Dia (In mm.) Length (In KM.) Remarks
1 DI 200 0.0235
Distribution Network
Sno. Pipe Type / Material Dia (In mm.) Length (In KM.) Remarks
1 HDPE 63 8.504
2 HDPE 75 1.888
3 HDPE 90 0.479
4 HDPE 140 0.163
5 HDPE 160 0.411
6 HDPE 180 1.383
7 HDPE 200 1.627
HSC Connection
Sno. Total Nos.
1 1013
Other Details
5.58
5.58
4.47
15-Feb-2025
16-Feb-2025