| Project Completion Certificate (Ground Water) | |||
|---|---|---|---|
| Scheme ID: 20082984 | Name of Scheme: UKASIA | No. of Villages: 1 | No. of Habitation Covered: 1 |
| Total Population Covered: 1617 | Base Year: 2022 | Intermediate Year: 2037 | Design Year: 2052 |
| Date of Completion (As per Contract): 31-Dec-2024 | Actual Date of Completion (Capex): 30-May-2024 | ||
| Tubewells | |||||
|---|---|---|---|---|---|
| Sno. | Description | Depth of Strainer (m) / Depth of Plain Pipe (m) | Location | Latitude | Longitude |
| 1 | Tubewell | 22.99 Mtr / 103.02 Mtr | UKASIA | 29.027667 | 77.466308 |
| Pumps | |||||
|---|---|---|---|---|---|
| Sno. | Type of Pump | Discharge (M³) / Head(Mtr.) | Location | Latitude | Longitude |
| 1 | Submersible | 150 LPM / 50 Mtr | UKASIA | 29.027667 | 77.466308 |
| OHT's | |||||
|---|---|---|---|---|---|
| Sno. | Structure | Capacity (In KL) / Staging Ht.(Mtr.) | Location | Latitude | Longitude |
| 1 | Direct Pumping Schemes | Direct Pumping Schemes | UKASIA | 29.027667 | 77.466308 |
| Clear Water Rising Main | ||||
|---|---|---|---|---|
| Sno. | Pipe Type / Material | Dia (In mm.) | Length (In KM.) | Remarks |
| 1 | DI | 100 | 4.20 | |
| Distribution Network | ||||
|---|---|---|---|---|
| Sno. | Pipe Type / Material | Dia (In mm.) | Length (In KM.) | Remarks |
| 1 | HDPE | 63 | 3.533 | |
| 2 | HDPE | 90 | 0.225 | |
| 3 | HDPE | 110 | 0.089 | |
| 4 | HDPE | 125 | 0.148 | |
| HSC Connection | |
|---|---|
| Sno. | Total Nos. |
| 1 | 315 |