Project Completion Certificate (Ground Water)
Scheme ID: 20083841 Name of Scheme: CHHITUNI WSS No. of Villages: 1 No. of Habitation Covered: 8
Total Population Covered: 2190 Base Year: 2023 Intermediate Year: 2038 Design Year: 2053
Date of Completion (As per Contract): 26-Dec-2023 Actual Date of Completion (Capex): 20-May-2025
Tubewells
Sno. Description Depth of Strainer (m) / Depth of Plain Pipe (m) Location Latitude Longitude
1 Lowering of tubewell assembly 18/76.8 CHHITUNI 26.499666 82.5133
Pumps
Sno. Type of Pump Discharge (M³) / Head(Mtr.) Location Latitude Longitude
1 ACsubmersible pumping 10HP 460/47 CHHITUNI 26.499666 82.5133
OHT's
Sno. Structure Capacity (In KL) / Staging Ht.(Mtr.) Location Latitude Longitude
1 RCC 125/16 CHHITUNI 26.500 82.516
Clear Water Rising Main
Sno. Pipe Type / Material Dia (In mm.) Length (In KM.) Remarks
1 DI-K7 100 0.032
Distribution Network
Sno. Pipe Type / Material Dia (In mm.) Length (In KM.) Remarks
1 Pipe PN-6: Class PE-100 90 1.144
2 Pipe PN-6: Class PE-100 75 1.923
3 Pipe PN-6: Class PE-100 63 6.794
4 Pipe PN-6: Class PE-100 110 0.138
5 Pipe PN-6: Class PE-100 140 0.403
6 Pipe PN-6: Class PE-100 160 0.014
HSC Connection
Sno. Total Nos.
1 334
Other Details
1.95
1.99
1.99
19-May-2025
20-May-2025