Project Completion Certificate (Ground Water)
Scheme ID: 20084413 Name of Scheme: PAHARPUR SHRIRAMPUR & SARAIYA KAMAURA WSS No. of Villages: 2 No. of Habitation Covered: 4
Total Population Covered: 3930 Base Year: 2023 Intermediate Year: 2038 Design Year: 2053
Date of Completion (As per Contract): 22-Jul-2023 Actual Date of Completion (Capex): 25-Sep-2023
Tubewells
Sno. Description Depth of Strainer (m) / Depth of Plain Pipe (m) Location Latitude Longitude
1 TUBEWELL 20/70 PAHARPUR SHREERAMPUR 26.135894 82.404928
Pumps
Sno. Type of Pump Discharge (M³) / Head(Mtr.) Location Latitude Longitude
1 PUMP 854/45 PAHARPUR SHREERAMPUR 26.135894 82.404928
OHT's
Sno. Structure Capacity (In KL) / Staging Ht.(Mtr.) Location Latitude Longitude
1 ZINC ALUM 250/14 PAHARPUR SHREERAMPUR 26.135894 82.404928
Clear Water Rising Main
Sno. Pipe Type / Material Dia (In mm.) Length (In KM.) Remarks
1 DI K-9 125 .035
Distribution Network
Sno. Pipe Type / Material Dia (In mm.) Length (In KM.) Remarks
1 HDPE 63 25.893
2 HDPE 75 0.823
3 HDPE 90 2.188
4 HDPE 110 2.353
5 HDPE 125 2.442
6 HDPE 140 0.752
7 HDPE 160 0.84
8 HDPE 180 1.665
HSC Connection
Sno. Total Nos.
1 779
Other Details
3.52
0.00
3.52
02-Feb-2025
03-Feb-2025