Project Completion Certificate (Ground Water)
Scheme ID: 20085648 Name of Scheme: SARAIYAN (GOGP) No. of Villages: 4 No. of Habitation Covered: 5
Total Population Covered: 5530 Base Year: 2022 Intermediate Year: 2037 Design Year: 2052
Date of Completion (As per Contract): 26-Jul-2023 Actual Date of Completion (Capex): 25-May-2023
Tubewells
Sno. Description Depth of Strainer (m) / Depth of Plain Pipe (m) Location Latitude Longitude
1 Tubewells 32.06Mtr/ 109.25Mtr SARAIYAN (GOGP) 27.559931 80.282393
Pumps
Sno. Type of Pump Discharge (M³) / Head(Mtr.) Location Latitude Longitude
1 Submersible 1.3 M³ per Min /45Mtr SARAIYAN (GOGP) 27.559931 80.282393
OHT's
Sno. Structure Capacity (In KL) / Staging Ht.(Mtr.) Location Latitude Longitude
1 OHT-1 350KL/ 16Mtr SARAIYAN (GOGP) 27.559953 80.282337
Clear Water Rising Main
Sno. Pipe Type / Material Dia (In mm.) Length (In KM.) Remarks
1 D.I Pipe 200 0.02211
Distribution Network
Sno. Pipe Type / Material Dia (In mm.) Length (In KM.) Remarks
1 HDPE Pipe PN-6, Class PE-100 63 5.908
2 HDPE Pipe PN-6, Class PE-100 75 3.967
3 HDPE Pipe PN-6, Class PE-100 90 2.454
4 HDPE Pipe PN-6, Class PE-100 110 2.450
5 HDPE Pipe PN-6, Class PE-100 125 2.280
6 HDPE Pipe PN-6, Class PE-100 140 4.008
7 HDPE Pipe PN-6, Class PE-100 160 1.141
8 HDPE Pipe PN-6, Class PE-100 200 0.063
HSC Connection
Sno. Total Nos.
1 761
Other Details
4.11
0.00
4.02
24-Aug-2023
24-Dec-2024