Project Completion Certificate (Ground Water)
Scheme ID: 20085670 Name of Scheme: NEWADA KISUNPUR GARH WATER SUPPLY SCHEME No. of Villages: 2 No. of Habitation Covered: 13
Total Population Covered: 3882 Base Year: 2023 Intermediate Year: 2038 Design Year: 2053
Date of Completion (As per Contract): 27-Mar-2023 Actual Date of Completion (Capex): 22-Jun-2024
Tubewells
Sno. Description Depth of Strainer (m) / Depth of Plain Pipe (m) Location Latitude Longitude
1 TUBEWELL 29 M / 80.65 M NEWADA KISUNPUR GAR 26.306564 81.740416
Pumps
Sno. Type of Pump Discharge (M³) / Head(Mtr.) Location Latitude Longitude
1 SUBMERSIBLE 850 LPM / 54 M NEWADA KISUNPUR GAR 26.306564 81.740416
OHT's
Sno. Structure Capacity (In KL) / Staging Ht.(Mtr.) Location Latitude Longitude
1 OHT 250 KL / 16 M NEWADA KISUNPUR GAR 26.306564 81.740416
Clear Water Rising Main
Sno. Pipe Type / Material Dia (In mm.) Length (In KM.) Remarks
1 DI 150 0.0227
Distribution Network
Sno. Pipe Type / Material Dia (In mm.) Length (In KM.) Remarks
1 HDPE 63 21.166
2 HDPE 90 4.777
3 HDPE 110 0.869
4 HDPE 140 0.720
5 HDPE 160 0.795
6 HDPE 180 0.142
HSC Connection
Sno. Total Nos.
1 854
Other Details
4.83
0.00
4.82
22-Sep-2024
23-Dec-2024