Project Completion Certificate (Ground Water)
Scheme ID: 20085692 Name of Scheme: ANI BAIJAL WATER SUPPLY SCHEME No. of Villages: 1 No. of Habitation Covered: 5
Total Population Covered: 3687 Base Year: 2023 Intermediate Year: 2038 Design Year: 2053
Date of Completion (As per Contract): 29-Apr-2024 Actual Date of Completion (Capex): 14-Aug-2024
Tubewells
Sno. Description Depth of Strainer (m) / Depth of Plain Pipe (m) Location Latitude Longitude
1 Tubewell 23.05/79.26 ANI BAIJAL 26.166317 81.175061
Pumps
Sno. Type of Pump Discharge (M³) / Head(Mtr.) Location Latitude Longitude
1 VT Punp -1 800LPM/52 ANI BAIJAL 26.166317 81.175061
OHT's
Sno. Structure Capacity (In KL) / Staging Ht.(Mtr.) Location Latitude Longitude
1 OHT 225KL / 14 mtr ANI BAIJAL 26.166317 81.175061
Clear Water Rising Main
Sno. Pipe Type / Material Dia (In mm.) Length (In KM.) Remarks
1 DI K-7 150 21.40
Distribution Network
Sno. Pipe Type / Material Dia (In mm.) Length (In KM.) Remarks
1 HDPE PN-6 63 12.35
2 HDPE PN-6 90 1.83
3 HDPE PN-6 110 1.84
4 HDPE PN-6 140 0.13
5 HDPE PN-6 200 0.01
HSC Connection
Sno. Total Nos.
1 760
Other Details
3.86
0.00
3.84
15-Nov-2024
16-Feb-2025