| Project Completion Certificate (Ground Water) | |||
|---|---|---|---|
| Scheme ID: 20085825 | Name of Scheme: KAIMA WATER SUPPLY SCHEME | No. of Villages: 1 | No. of Habitation Covered: 7 |
| Total Population Covered: 2762 | Base Year: 2022 | Intermediate Year: 2037 | Design Year: 2052 |
| Date of Completion (As per Contract): 22-Mar-2025 | Actual Date of Completion (Capex): 14-Sep-2024 | ||
| Tubewells | |||||
|---|---|---|---|---|---|
| Sno. | Description | Depth of Strainer (m) / Depth of Plain Pipe (m) | Location | Latitude | Longitude |
| 1 | 150MM PLAIN PIPE | 48.80 | KAIMA | 26.433507 | 81.712631 |
| 2 | 150MM SLOTTED PIPE | 12 | KAIMA | 26.433507 | 81.712631 |
| 3 | 200MM PLAIN PIPE | 62.50 | KAIMA | 26.433507 | 81.712631 |
| 4 | 200MM SLOTTED PIPE | 10 | KAIMA | 26.433507 | 81.712631 |
| Pumps | |||||
|---|---|---|---|---|---|
| Sno. | Type of Pump | Discharge (M³) / Head(Mtr.) | Location | Latitude | Longitude |
| 1 | SUBMERSIBLE PUMP | 240LPM / 54MTR | KAIMA | 26.433507 | 81.712631 |
| OHT's | |||||
|---|---|---|---|---|---|
| Sno. | Structure | Capacity (In KL) / Staging Ht.(Mtr.) | Location | Latitude | Longitude |
| 1 | OVER HEAD TANK | 100KL / 16MTR | KAIMA | 26.433507 | 81.712631 |
| Clear Water Rising Main | ||||
|---|---|---|---|---|
| Sno. | Pipe Type / Material | Dia (In mm.) | Length (In KM.) | Remarks |
| 1 | DI PIPE | 100 | 0.025 | |
| Distribution Network | ||||
|---|---|---|---|---|
| Sno. | Pipe Type / Material | Dia (In mm.) | Length (In KM.) | Remarks |
| 1 | HDPE PIPE | 90 | 0.549 | |
| 2 | HDPE PIPE | 75 | 0.761 | |
| 3 | HDPE PIPE | 63 | 19.673 | |
| 4 | HDPE PIPE | 110 | 2.170 | |
| 5 | HDPE PIPE | 125 | 1.664 | |
| 6 | HDPE PIPE | 140 | 0.019 | |
| HSC Connection | |
|---|---|
| Sno. | Total Nos. |
| 1 | 663 |