| Project Completion Certificate (Ground Water) | |||
|---|---|---|---|
| Scheme ID: 20085872 | Name of Scheme: LAKHANKHEDA | No. of Villages: 1 | No. of Habitation Covered: 1 |
| Total Population Covered: 2100 | Base Year: 2023 | Intermediate Year: 2038 | Design Year: 2053 |
| Date of Completion (As per Contract): 14-Mar-2024 | Actual Date of Completion (Capex): 03-Dec-2024 | ||
| Tubewells | |||||
|---|---|---|---|---|---|
| Sno. | Description | Depth of Strainer (m) / Depth of Plain Pipe (m) | Location | Latitude | Longitude |
| 1 | DEEP TUBEWELL (450 LPM) | 18.04/117.47 | LAKHANA KHEDA | 26.060742 | 80.521705 |
| Pumps | |||||
|---|---|---|---|---|---|
| Sno. | Type of Pump | Discharge (M³) / Head(Mtr.) | Location | Latitude | Longitude |
| 1 | 12.5 HP SUBMERSIBLE PUMP | 450 LPM/60 MTR | LAKHANA KHEDA | 26.060742 | 80.521705 |
| OHT's | |||||
|---|---|---|---|---|---|
| Sno. | Structure | Capacity (In KL) / Staging Ht.(Mtr.) | Location | Latitude | Longitude |
| 1 | ELEVATED STORAGE RESERVOIR | 125KL/14M | LAKHANA KHEDA | 26.060742 | 80.521705 |
| Clear Water Rising Main | ||||
|---|---|---|---|---|
| Sno. | Pipe Type / Material | Dia (In mm.) | Length (In KM.) | Remarks |
| 1 | DI K-7 | 100 | 0.04 | |
| Distribution Network | ||||
|---|---|---|---|---|
| Sno. | Pipe Type / Material | Dia (In mm.) | Length (In KM.) | Remarks |
| 1 | HDPE PIPE | 63 | 3.918 | |
| 2 | HDPE PIPE | 75 | 0.085 | |
| 3 | HDPE PIPE | 90 | 0.415 | |
| 4 | HDPE PIPE | 125 | 1.171 | |
| 5 | HDPE PIPE | 140 | 0.329 | |
| 6 | HDPE PIPE | 180 | 0.144 | |
| HSC Connection | |
|---|---|
| Sno. | Total Nos. |
| 1 | 430 |