Project Completion Certificate (Ground Water)
Scheme ID: 20087631 Name of Scheme: Nasirpur Banwari Water supply Scheme No. of Villages: 1 No. of Habitation Covered: 1
Total Population Covered: 2045 Base Year: 2022 Intermediate Year: 2037 Design Year: 2052
Date of Completion (As per Contract): 08-Jun-2023 Actual Date of Completion (Capex): 01-Dec-2024
Tubewells
Sno. Description Depth of Strainer (m) / Depth of Plain Pipe (m) Location Latitude Longitude
Pumps
Sno. Type of Pump Discharge (M³) / Head(Mtr.) Location Latitude Longitude
OHT's
Sno. Structure Capacity (In KL) / Staging Ht.(Mtr.) Location Latitude Longitude
Clear Water Rising Main
Sno. Pipe Type / Material Dia (In mm.) Length (In KM.) Remarks
Distribution Network
Sno. Pipe Type / Material Dia (In mm.) Length (In KM.) Remarks
1 HDPE PIPE PN -6: CLASS PE -100 63 3.86
2 HDPE PIPE PN -6: CLASS PE -100 75 0.58
3 HDPE PIPE PN -6: CLASS PE -100 90 0.01
4 HDPE PIPE PN -6: CLASS PE -100 110 0.01
5 HDPE PIPE PN -6: CLASS PE -100 125 0.20
6 HDPE PIPE PN -6: CLASS PE -100 140 0.08
HSC Connection
Sno. Total Nos.
1 320
Other Details
1.41
1.41
1.39
28-Feb-2025
01-Mar-2025