Project Completion Certificate (Ground Water)
Scheme ID: 20088192 Name of Scheme: MANSDI GRAM PANCHAYAT WATER SUPPLY SCHEME No. of Villages: 1 No. of Habitation Covered: 5
Total Population Covered: 2120 Base Year: 2023 Intermediate Year: 2038 Design Year: 2038
Date of Completion (As per Contract): 21-Mar-2025 Actual Date of Completion (Capex): 21-Mar-2025
Tubewells
Sno. Description Depth of Strainer (m) / Depth of Plain Pipe (m) Location Latitude Longitude
1 plain pipe 150 mm dia 38 TW 25.851550 83.448708
2 slotted pipe 200 mm dia 18 TW 25.851550 83.448708
Pumps
Sno. Type of Pump Discharge (M³) / Head(Mtr.) Location Latitude Longitude
1 SUBMERSIBLE PUMP 420LPM/42 TW 25.851550 83.448708
OHT's
Sno. Structure Capacity (In KL) / Staging Ht.(Mtr.) Location Latitude Longitude
1 Zincalume tank 125/12 OHT 25.851550 83.448708
Clear Water Rising Main
Sno. Pipe Type / Material Dia (In mm.) Length (In KM.) Remarks
1 HDPE Pipe PN-6: Class PE-100 63 8.52
2 HDPE Pipe PN-6: Class PE-100 75 1.89
3 HDPE Pipe PN-6: Class PE-100 90 .883
4 HDPE Pipe PN-6: Class PE-100 110 0.527
5 HDPE Pipe PN-6: Class PE-100 125 0.770
6 HDPE Pipe PN-6: Class PE-100 140 0.252
7 HDPE Pipe PN-6: Class PE-100 160 0.049
8 HDPE Pipe PN-6: Class PE-100 180 0.016
Distribution Network
Sno. Pipe Type / Material Dia (In mm.) Length (In KM.) Remarks
1 DI K7 80 0.03
HSC Connection
Sno. Total Nos.
1 473
Other Details
1.93
0.00
1.94
20-Mar-2025