| Project Completion Certificate (Ground Water) | |||
|---|---|---|---|
| Scheme ID: 20089241 | Name of Scheme: Akbarabad | No. of Villages: 1 | No. of Habitation Covered: 2 |
| Total Population Covered: 1560 | Base Year: 2023 | Intermediate Year: 2038 | Design Year: 2053 |
| Date of Completion (As per Contract): 13-Mar-2024 | Actual Date of Completion (Capex): 28-Feb-2025 | ||
| Tubewells | |||||
|---|---|---|---|---|---|
| Sno. | Description | Depth of Strainer (m) / Depth of Plain Pipe (m) | Location | Latitude | Longitude |
| 1 | Tube well 140 LPM | 16/139.85 | Akbarabad | 26.100545 | 80.519801 |
| Pumps | |||||
|---|---|---|---|---|---|
| Sno. | Type of Pump | Discharge (M³) / Head(Mtr.) | Location | Latitude | Longitude |
| 1 | Submersible 7.5 HP | 140/55 | Akbarabad | 26.100545 | 80.519801 |
| OHT's | |||||
|---|---|---|---|---|---|
| Sno. | Structure | Capacity (In KL) / Staging Ht.(Mtr.) | Location | Latitude | Longitude |
| 1 | OHT-1 | 50/14 | Akbarabad | 26.100545 | 80.519801 |
| Clear Water Rising Main | ||||
|---|---|---|---|---|
| Sno. | Pipe Type / Material | Dia (In mm.) | Length (In KM.) | Remarks |
| 1 | DI K-7 | 80 | 40 | |
| Distribution Network | ||||
|---|---|---|---|---|
| Sno. | Pipe Type / Material | Dia (In mm.) | Length (In KM.) | Remarks |
| 1 | HDPE | 63 | 5934 | |
| 2 | HDPE | 75 | 1135 | |
| 3 | HDPE | 90 | 154 | |
| 4 | HDPE | 110 | 41 | |
| 5 | HDPE | 140 | 244 | |
| HSC Connection | |
|---|---|
| Sno. | Total Nos. |
| 1 | 420 |