Project Completion Certificate (Ground Water)
Scheme ID: 20091164 Name of Scheme: Sarai pratham PWS No. of Villages: 1 No. of Habitation Covered: 3
Total Population Covered: 3125 Base Year: 2023 Intermediate Year: 2038 Design Year: 2053
Date of Completion (As per Contract): 01-Jun-2024 Actual Date of Completion (Capex): 04-May-2025
Tubewells
Sno. Description Depth of Strainer (m) / Depth of Plain Pipe (m) Location Latitude Longitude
Pumps
Sno. Type of Pump Discharge (M³) / Head(Mtr.) Location Latitude Longitude
OHT's
Sno. Structure Capacity (In KL) / Staging Ht.(Mtr.) Location Latitude Longitude
Clear Water Rising Main
Sno. Pipe Type / Material Dia (In mm.) Length (In KM.) Remarks
1 DI 150 0 .01
Distribution Network
Sno. Pipe Type / Material Dia (In mm.) Length (In KM.) Remarks
1 125 63 4.623
2 HDPE 90 3.918
3 HDPE 110 .904
4 HDPE 125 .276
5 HDPE 140 1.876
HSC Connection
Sno. Total Nos.
Other Details
2.97
0.00
0.00
03-May-2025
05-May-2025