Project Completion Certificate (Ground Water)
Scheme ID: 20092702 Name of Scheme: minapur No. of Villages: 1 No. of Habitation Covered: 1
Total Population Covered: 1632 Base Year: 2023 Intermediate Year: 2038 Design Year: 2023
Date of Completion (As per Contract): 30-Apr-2023 Actual Date of Completion (Capex): 31-Dec-2023
Tubewells
Sno. Description Depth of Strainer (m) / Depth of Plain Pipe (m) Location Latitude Longitude
1 Tubewell 5/65.85 MINAPUR 26°32'42"N 79°82'69"E
Pumps
Sno. Type of Pump Discharge (M³) / Head(Mtr.) Location Latitude Longitude
1 Submersible 150/71 MINAPUR 26°32'42"N 79°82'69"E
OHT's
Sno. Structure Capacity (In KL) / Staging Ht.(Mtr.) Location Latitude Longitude
1 OHT-14 50/12 MINAPUR 26°32'42"N 79°82'69"E
Clear Water Rising Main
Sno. Pipe Type / Material Dia (In mm.) Length (In KM.) Remarks
1 DI 100 0.020
Distribution Network
Sno. Pipe Type / Material Dia (In mm.) Length (In KM.) Remarks
1 HDPE 63 4.09
2 HDPE 90 0.737
3 HDPE 110 0.464
4 HDPE 140 0.183
HSC Connection
Sno. Total Nos.
1 330
Other Details
2.04
0.00
165.51
15-Apr-2024
16-Apr-2024