Project Completion Certificate (Ground Water)
Scheme ID: 20092722 Name of Scheme: SHIBRAIMATH MVS No. of Villages: 3 No. of Habitation Covered: 3
Total Population Covered: 2634 Base Year: 2023 Intermediate Year: 2038 Design Year: 2053
Date of Completion (As per Contract): 30-May-2025 Actual Date of Completion (Capex): 01-Jul-2024
Tubewells
Sno. Description Depth of Strainer (m) / Depth of Plain Pipe (m) Location Latitude Longitude
1 TUBEWELL 21M/114.50M SHIBRAIMATH 27.50793 79.31665
Pumps
Sno. Type of Pump Discharge (M³) / Head(Mtr.) Location Latitude Longitude
1 SUBMERSIBLE PUMP 600LPM/61M SHIBRAIMATH 27.50793 79.31665
OHT's
Sno. Structure Capacity (In KL) / Staging Ht.(Mtr.) Location Latitude Longitude
1 OHT 175KL/14M SHIBRAIMATH 27.50793 79.31665
Clear Water Rising Main
Sno. Pipe Type / Material Dia (In mm.) Length (In KM.) Remarks
1 DI 100 0.018
Distribution Network
Sno. Pipe Type / Material Dia (In mm.) Length (In KM.) Remarks
1 HDPE PIPE 90 0.715
2 HDPE PIPE 63 4.664
3 HDPE PIPE 110 0.382
4 HDPE PIPE 140 1.363
5 HDPE PIPE 160 0.796
HSC Connection
Sno. Total Nos.
Other Details
2.91
2.84
2.91
01-Jul-2024
02-Jul-2024