Project Completion Certificate (Ground Water)
Scheme ID: 20094809 Name of Scheme: JAMALPUR VILLAGE WATER SUPPLY SCHEME No. of Villages: 1 No. of Habitation Covered: 1
Total Population Covered: 2428 Base Year: 2022 Intermediate Year: 2037 Design Year: 2052
Date of Completion (As per Contract): 20-Mar-2023 Actual Date of Completion (Capex): 07-Feb-2024
Tubewells
Sno. Description Depth of Strainer (m) / Depth of Plain Pipe (m) Location Latitude Longitude
1 TUBEWELL 23.65M/87.50M JAMALPUR 28.414333 77.640681
Pumps
Sno. Type of Pump Discharge (M³) / Head(Mtr.) Location Latitude Longitude
1 SUBMERCIBLE 600LPM/51M JAMALPUR 28.414333 77.640681
OHT's
Sno. Structure Capacity (In KL) / Staging Ht.(Mtr.) Location Latitude Longitude
1 OHT 150KL/14M JAMALPUR 28.414333 77.640681
Clear Water Rising Main
Sno. Pipe Type / Material Dia (In mm.) Length (In KM.) Remarks
1 DI 100 0.019
Distribution Network
Sno. Pipe Type / Material Dia (In mm.) Length (In KM.) Remarks
1 HDPE 63 3.210
2 HDPE 75 1.121
3 HDPE 90 0.167
4 HDPE 110 0.165
5 HDPE 140 0.320
6 HDPE 160 0.480
HSC Connection
Sno. Total Nos.
1 448
Other Details
1.88
1.87
1.87
30-Mar-2024
01-Apr-2024