Project Completion Certificate (Ground Water)
Scheme ID: 20094905 Name of Scheme: MATAUR VILLAGE WATER SUPPLY SCHEME No. of Villages: 1 No. of Habitation Covered: 1
Total Population Covered: 2329 Base Year: 2022 Intermediate Year: 2037 Design Year: 2052
Date of Completion (As per Contract): 31-Oct-2024 Actual Date of Completion (Capex): 01-Dec-2024
Tubewells
Sno. Description Depth of Strainer (m) / Depth of Plain Pipe (m) Location Latitude Longitude
1 Tubewell 28m/76m mataur 28.919992 77.452726
Pumps
Sno. Type of Pump Discharge (M³) / Head(Mtr.) Location Latitude Longitude
1 Submersible 320LPM/51M mataur 28.919992 77.452726
OHT's
Sno. Structure Capacity (In KL) / Staging Ht.(Mtr.) Location Latitude Longitude
1 OHT 100/12 mataur 28.919992 77.452726
Clear Water Rising Main
Sno. Pipe Type / Material Dia (In mm.) Length (In KM.) Remarks
1 D.I 100 0.0172
Distribution Network
Sno. Pipe Type / Material Dia (In mm.) Length (In KM.) Remarks
1 HDPE 63 2.7848
2 HDPE 75 .1456
3 HDPE 90 .0603
4 HDPE 110 .1207
5 HDPE 125 .0851
6 HDPE 140 .1155
HSC Connection
Sno. Total Nos.
1 363
Other Details
1.36
1.35
1.35
27-Mar-2025
01-Apr-2025