| Project Completion Certificate (Ground Water) | |||
|---|---|---|---|
| Scheme ID: 20094912 | Name of Scheme: MATIALA VILLAGE WATER SUPPLY SCHEME | No. of Villages: 1 | No. of Habitation Covered: 1 |
| Total Population Covered: 2130 | Base Year: 2022 | Intermediate Year: 2033 | Design Year: 2052 |
| Date of Completion (As per Contract): 30-Sep-2024 | Actual Date of Completion (Capex): 30-Nov-2024 | ||
| Tubewells | |||||
|---|---|---|---|---|---|
| Sno. | Description | Depth of Strainer (m) / Depth of Plain Pipe (m) | Location | Latitude | Longitude |
| 1 | Tubewell | 24/105 | matiyala | 28.71663551 | 77.49712796 |
| Pumps | |||||
|---|---|---|---|---|---|
| Sno. | Type of Pump | Discharge (M³) / Head(Mtr.) | Location | Latitude | Longitude |
| 1 | Submersible | 300LPM/51M | Matiyala | 28.71663551 | 77.49712796 |
| OHT's | |||||
|---|---|---|---|---|---|
| Sno. | Structure | Capacity (In KL) / Staging Ht.(Mtr.) | Location | Latitude | Longitude |
| 1 | OHT | 100/12 | Matiyala | 28.71663551 | 77.49712796 |
| Clear Water Rising Main | ||||
|---|---|---|---|---|
| Sno. | Pipe Type / Material | Dia (In mm.) | Length (In KM.) | Remarks |
| 1 | D.I | 100 | 100 | 25 |
| Distribution Network | ||||
|---|---|---|---|---|
| Sno. | Pipe Type / Material | Dia (In mm.) | Length (In KM.) | Remarks |
| 1 | HDPE | 63 | 1.445 | |
| 2 | HDPE | 75 | .099 | |
| 3 | HDPE | 90 | .446 | |
| 4 | HDPE | 110 | .115 | |
| 5 | HDPE | 125 | 1.007 | |
| HSC Connection | |
|---|---|
| Sno. | Total Nos. |
| 1 | 338 |