Project Completion Certificate (Ground Water)
Scheme ID: 20095101 Name of Scheme: Purwa Rahat PWS No. of Villages: 1 No. of Habitation Covered: 1
Total Population Covered: 1474 Base Year: 2023 Intermediate Year: 2038 Design Year: 2033
Date of Completion (As per Contract): 31-Dec-2024 Actual Date of Completion (Capex): 19-May-2024
Tubewells
Sno. Description Depth of Strainer (m) / Depth of Plain Pipe (m) Location Latitude Longitude
Pumps
Sno. Type of Pump Discharge (M³) / Head(Mtr.) Location Latitude Longitude
OHT's
Sno. Structure Capacity (In KL) / Staging Ht.(Mtr.) Location Latitude Longitude
Clear Water Rising Main
Sno. Pipe Type / Material Dia (In mm.) Length (In KM.) Remarks
Distribution Network
Sno. Pipe Type / Material Dia (In mm.) Length (In KM.) Remarks
1 HDPE 63 1.681
2 HDPE 90 1.467
3 HDPE 110 .396
HSC Connection
Sno. Total Nos.
Other Details
1.05
0.00
109.54
08-May-2024
09-May-2024