Project Completion Certificate (Ground Water)
Scheme ID: 20095819 Name of Scheme: ANJANA KABIR No. of Villages: 3 No. of Habitation Covered: 3
Total Population Covered: 3490 Base Year: 2023 Intermediate Year: 2038 Design Year: 2053
Date of Completion (As per Contract): 14-May-2024 Actual Date of Completion (Capex): 30-Jun-2025
Tubewells
Sno. Description Depth of Strainer (m) / Depth of Plain Pipe (m) Location Latitude Longitude
1 Tube well 17.2 M /89.40 m ANJANA KABIR 25°.642138" N 81.169628"E
Pumps
Sno. Type of Pump Discharge (M³) / Head(Mtr.) Location Latitude Longitude
1 Submersible 690 LPM / 60 M ANJANA KABIR 25°.642138" N 81.169628"E
OHT's
Sno. Structure Capacity (In KL) / Staging Ht.(Mtr.) Location Latitude Longitude
1 OHT-1 200 KL / 14 M ANJANA KABIR 25°.642138" N 81.169628"E
Clear Water Rising Main
Sno. Pipe Type / Material Dia (In mm.) Length (In KM.) Remarks
1 D.I. K-9 125 0.02520
Distribution Network
Sno. Pipe Type / Material Dia (In mm.) Length (In KM.) Remarks
1 HDPE 200 0.3166
2 HDPE 180 0.8239
3 HDPE 160 0.4518
4 HDPE 140 0.614
5 HDPE 125 0.463
6 HDPE 110 0.7245
7 HDPE 90 0.294
8 HDPE 75 1.2395
9 HDPE 63 5.6648
HSC Connection
Sno. Total Nos.
1 695
Other Details
2.70
0.00
3.18
12-Mar-2025
13-Mar-2025