Project Completion Certificate (Ground Water)
Scheme ID: 20095919 Name of Scheme: SIHARI PATTI No. of Villages: 2 No. of Habitation Covered: 3
Total Population Covered: 2330 Base Year: 2023 Intermediate Year: 2038 Design Year: 2053
Date of Completion (As per Contract): 13-Aug-2023 Actual Date of Completion (Capex): 30-Jun-2025
Tubewells
Sno. Description Depth of Strainer (m) / Depth of Plain Pipe (m) Location Latitude Longitude
1 1 132 SIHARI PATTI 25.56751500 81.172095
Pumps
Sno. Type of Pump Discharge (M³) / Head(Mtr.) Location Latitude Longitude
1 1 55M/12.5 BHP SIHARI PATTI 25.56771500 81.172095
OHT's
Sno. Structure Capacity (In KL) / Staging Ht.(Mtr.) Location Latitude Longitude
1 1 150KL/12M SIHARI PATTI 25.56741500 81.172095
Clear Water Rising Main
Sno. Pipe Type / Material Dia (In mm.) Length (In KM.) Remarks
1 DI PIPE K-9 100 0.0291
Distribution Network
Sno. Pipe Type / Material Dia (In mm.) Length (In KM.) Remarks
1 HDPE PIPE 125 1.7970
2 HDPE PIPE 110 0.0645
3 HDPE PIPE 90 0.9017
4 HDPE PIPE 75 1.5375
5 HDPE PIPE 63 3.7159
6 HDPE PIPE 160 1.137
7 HDPE PIPE 160 1.137
HSC Connection
Sno. Total Nos.
1 489
Other Details
2.19
2.19
2.19
07-Dec-2024
08-Dec-2024