| Project Completion Certificate (Ground Water) | |||
|---|---|---|---|
| Scheme ID: 20096494 | Name of Scheme: MALUAPUR GRAM PANCHAYAT VILLAGE WATER SUPPLY SCHEME | No. of Villages: 1 | No. of Habitation Covered: 2 |
| Total Population Covered: 3230 | Base Year: 2022 | Intermediate Year: 2037 | Design Year: 2052 |
| Date of Completion (As per Contract): 19-Aug-2024 | Actual Date of Completion (Capex): 21-Dec-2024 | ||
| Tubewells | |||||
|---|---|---|---|---|---|
| Sno. | Description | Depth of Strainer (m) / Depth of Plain Pipe (m) | Location | Latitude | Longitude |
| 1 | TUBEWELL | 18/94.38 | MALUPUR | 27.739559 | 79.663615 |
| Pumps | |||||
|---|---|---|---|---|---|
| Sno. | Type of Pump | Discharge (M³) / Head(Mtr.) | Location | Latitude | Longitude |
| 1 | VT PUMP 1 | 40.74/45 | MALUPUR | 27.739559 | 79.663615 |
| OHT's | |||||
|---|---|---|---|---|---|
| Sno. | Structure | Capacity (In KL) / Staging Ht.(Mtr.) | Location | Latitude | Longitude |
| 1 | OHT 1 | 200/16 | MALUPUR | 27.739628 | 79.663618 |
| Clear Water Rising Main | ||||
|---|---|---|---|---|
| Sno. | Pipe Type / Material | Dia (In mm.) | Length (In KM.) | Remarks |
| 1 | K-7 | 125 | 0.030 | |
| Distribution Network | ||||
|---|---|---|---|---|
| Sno. | Pipe Type / Material | Dia (In mm.) | Length (In KM.) | Remarks |
| 1 | HDPE / 6KG | 63 | 2.164 | |
| 2 | HDPE / 6KG | 75 | 0.868 | |
| 3 | HDPE / 6KG | 90 | 0.235 | |
| 4 | HDPE / 6KG | 110 | 0.173 | |
| 5 | HDPE / 6KG | 140 | 0.806 | |
| 6 | HDPE / 6KG | 160 | 0.529 | |
| 7 | HDPE / 6KG | 200 | 0.489 | |
| HSC Connection | |
|---|---|
| Sno. | Total Nos. |
| 1 | 521 |