Project Completion Certificate (Ground Water)
Scheme ID: 20096848 Name of Scheme: KUSHMAURI JJM SCHEME No. of Villages: 3 No. of Habitation Covered: 3
Total Population Covered: 3507 Base Year: 2022 Intermediate Year: 2037 Design Year: 2052
Date of Completion (As per Contract): 09-Apr-2023 Actual Date of Completion (Capex): 11-Jun-2024
Tubewells
Sno. Description Depth of Strainer (m) / Depth of Plain Pipe (m) Location Latitude Longitude
1 Tubewell 24 M / 120 M Kushmouri 28.070809 80.374294
Pumps
Sno. Type of Pump Discharge (M³) / Head(Mtr.) Location Latitude Longitude
1 Submersible 720 LPM / 43 M Kushmouri 28.070809 c
OHT's
Sno. Structure Capacity (In KL) / Staging Ht.(Mtr.) Location Latitude Longitude
1 OHT 200 KL / 16 M Kushmouri 28.070809 28.070809
Clear Water Rising Main
Sno. Pipe Type / Material Dia (In mm.) Length (In KM.) Remarks
1 D.I. Pipe 125 0.018
Distribution Network
Sno. Pipe Type / Material Dia (In mm.) Length (In KM.) Remarks
1 160 mm dia HDPE Pipe PN-6: Class PE-100 160 2.505
2 140 mm dia HDPE Pipe PN-6: Class PE-100 140 1.657
3 110 mm dia HDPE Pipe PN-6: Class PE-100 110 1.643
4 90 mm dia HDPE Pipe PN-6: Class PE-100 90 0.293
5 63 mm dia HDPE Pipe PN-6: Class PE-100 63 12.873
HSC Connection
Sno. Total Nos.
1 523
Other Details
281.04
0.00
274.64
11-Jun-2024
19-Nov-2024