Project Completion Certificate (Ground Water)
Scheme ID: 20097161 Name of Scheme: Bhapasa Water Supply System No. of Villages: 1 No. of Habitation Covered: 1
Total Population Covered: 1640 Base Year: 2022 Intermediate Year: 2037 Design Year: 2052
Date of Completion (As per Contract): 21-Oct-2024 Actual Date of Completion (Capex): 01-Jun-2026
Tubewells
Sno. Description Depth of Strainer (m) / Depth of Plain Pipe (m) Location Latitude Longitude
1 Tubewell 15/121.87 Bhapasa 26.7397 83.2139
Pumps
Sno. Type of Pump Discharge (M³) / Head(Mtr.) Location Latitude Longitude
1 Submersible Pump 21/39 Bhapasa 26.7397 83.2139
OHT's
Sno. Structure Capacity (In KL) / Staging Ht.(Mtr.) Location Latitude Longitude
1 Overhead Tank-1 100/12 Bhapasa 26.7397 83.2139
Clear Water Rising Main
Sno. Pipe Type / Material Dia (In mm.) Length (In KM.) Remarks
1 DI 100 0.015 Laying Completed
Distribution Network
Sno. Pipe Type / Material Dia (In mm.) Length (In KM.) Remarks
1 HDPE 63 2.10 Laying Completed
2 HDPE 75 0.19 Laying Completed
3 HDPE 90 0.33 Laying Completed
4 HDPE 110 .11 Laying Completed
5 HDPE 140 0.13 Laying Completed
HSC Connection
Sno. Total Nos.
Other Details
1.30
0.00
1.30
13-Jan-2026
18-Jun-2026