| Project Completion Certificate (Ground Water) | |||
|---|---|---|---|
| Scheme ID: 20097194 | Name of Scheme: Tenuwa Water Supply System | No. of Villages: 3 | No. of Habitation Covered: 3 |
| Total Population Covered: 3700 | Base Year: 2022 | Intermediate Year: 2037 | Design Year: 2052 |
| Date of Completion (As per Contract): 12-Apr-2025 | Actual Date of Completion (Capex): 06-Mar-2025 | ||
| Tubewells | |||||
|---|---|---|---|---|---|
| Sno. | Description | Depth of Strainer (m) / Depth of Plain Pipe (m) | Location | Latitude | Longitude |
| 1 | Tubewell | 24/116.86 | Tenuwa | 26.7214 | 83.2350 |
| Pumps | |||||
|---|---|---|---|---|---|
| Sno. | Type of Pump | Discharge (M³) / Head(Mtr.) | Location | Latitude | Longitude |
| 1 | Submersible Pump | 48/43 | Tenuwa | 26.7214 | 83.2350 |
| OHT's | |||||
|---|---|---|---|---|---|
| Sno. | Structure | Capacity (In KL) / Staging Ht.(Mtr.) | Location | Latitude | Longitude |
| 1 | Overhead Tank-1 | 225/14 | Tenuwa | 26.7214 | 83.2350 |
| Clear Water Rising Main | ||||
|---|---|---|---|---|
| Sno. | Pipe Type / Material | Dia (In mm.) | Length (In KM.) | Remarks |
| 1 | DI | 150 | 0.030 | Laying Completed |
| Distribution Network | ||||
|---|---|---|---|---|
| Sno. | Pipe Type / Material | Dia (In mm.) | Length (In KM.) | Remarks |
| 1 | HDPE | 63 | 5.643 | Laying Completed |
| 2 | HDPE | 110 | 0.336 | Laying Completed |
| 3 | HDPE | 140 | 1.487 | Laying Completed |
| HSC Connection | |
|---|---|
| Sno. | Total Nos. |
| 1 | 604 |