| Project Completion Certificate (Ground Water) | |||
|---|---|---|---|
| Scheme ID: 20097449 | Name of Scheme: AHINDA | No. of Villages: 1 | No. of Habitation Covered: 2 |
| Total Population Covered: 1950 | Base Year: 2023 | Intermediate Year: 2038 | Design Year: 2053 |
| Date of Completion (As per Contract): 18-Mar-2025 | Actual Date of Completion (Capex): 30-Jun-2025 | ||
| Tubewells | |||||
|---|---|---|---|---|---|
| Sno. | Description | Depth of Strainer (m) / Depth of Plain Pipe (m) | Location | Latitude | Longitude |
| 1 | Tube well | 18/132 | AHINDA | 25°.9470016" N | 81.05691833"E |
| Pumps | |||||
|---|---|---|---|---|---|
| Sno. | Type of Pump | Discharge (M³) / Head(Mtr.) | Location | Latitude | Longitude |
| 1 | Submersible | 420/55 | AHINDA | 25°.9470016" N | 81.05691833"E |
| OHT's | |||||
|---|---|---|---|---|---|
| Sno. | Structure | Capacity (In KL) / Staging Ht.(Mtr.) | Location | Latitude | Longitude |
| 1 | OHT-1 | 125/12 | AHINDA | 25°.9470016" N | 81.05691833"E |
| Clear Water Rising Main | ||||
|---|---|---|---|---|
| Sno. | Pipe Type / Material | Dia (In mm.) | Length (In KM.) | Remarks |
| 1 | D.I. K,9 | 80 | 0.01630 | |
| Distribution Network | ||||
|---|---|---|---|---|
| Sno. | Pipe Type / Material | Dia (In mm.) | Length (In KM.) | Remarks |
| 1 | HDPE | 140 | 0.0653 | |
| 2 | HDPE | 125 | 0.1829 | |
| 3 | HDPE | 110 | 0.0903 | |
| 4 | HDPE | 90 | 0.0947 | |
| 5 | HDPE | 75 | 1.2397 | |
| 6 | HDPE | 63 | 4.4309 | |
| HSC Connection | |
|---|---|
| Sno. | Total Nos. |
| 1 | 340 |