| Project Completion Certificate (Ground Water) | |||
|---|---|---|---|
| Scheme ID: 20097513 | Name of Scheme: GUDAURA | No. of Villages: 1 | No. of Habitation Covered: 2 |
| Total Population Covered: 3500 | Base Year: 2023 | Intermediate Year: 2038 | Design Year: 2053 |
| Date of Completion (As per Contract): 18-Mar-2025 | Actual Date of Completion (Capex): 30-Jun-2025 | ||
| Tubewells | |||||
|---|---|---|---|---|---|
| Sno. | Description | Depth of Strainer (m) / Depth of Plain Pipe (m) | Location | Latitude | Longitude |
| 1 | Tube well | 24/118 | GUDAURA | 25°.6757833" N | 81.0690468"E |
| Pumps | |||||
|---|---|---|---|---|---|
| Sno. | Type of Pump | Discharge (M³) / Head(Mtr.) | Location | Latitude | Longitude |
| 1 | Submersible | 700/60 | GUDAURA | 25°.6757833" N | 81.0690468"E |
| OHT's | |||||
|---|---|---|---|---|---|
| Sno. | Structure | Capacity (In KL) / Staging Ht.(Mtr.) | Location | Latitude | Longitude |
| 1 | OHT-1 | 225/14 | GUDAURA | 25°.6757833" N | 81.0690468"E |
| Clear Water Rising Main | ||||
|---|---|---|---|---|
| Sno. | Pipe Type / Material | Dia (In mm.) | Length (In KM.) | Remarks |
| 1 | D.I. K,9 | 100 | 0.03010 | |
| Distribution Network | ||||
|---|---|---|---|---|
| Sno. | Pipe Type / Material | Dia (In mm.) | Length (In KM.) | Remarks |
| 1 | HDPE | 200 | 0.12 | |
| 2 | HDPE | 180 | 0.647 | |
| 3 | HDPE | 160 | 0.3581 | |
| 4 | HDPE | 140 | 0.3248 | |
| 5 | HDPE | 125 | 1.032 | |
| 6 | HDPE | 110 | 0.2034 | |
| 7 | HDPE | 90 | 1.239 | |
| 8 | HDPE | 75 | 1.3157 | |
| 9 | HDPE | 63 | 5.2999 | |
| HSC Connection | |
|---|---|
| Sno. | Total Nos. |
| 1 | 784 |