Project Completion Certificate (Ground Water)
Scheme ID: 20097559 Name of Scheme: ADHAURI JJM SCHEME No. of Villages: 1 No. of Habitation Covered: 1
Total Population Covered: 1270 Base Year: 2022 Intermediate Year: 2037 Design Year: 2052
Date of Completion (As per Contract): 27-Jan-2025 Actual Date of Completion (Capex): 01-Jan-2024
Tubewells
Sno. Description Depth of Strainer (m) / Depth of Plain Pipe (m) Location Latitude Longitude
1 Tubewell 18 / 93.80 Adori 27.658743 80.490233
Pumps
Sno. Type of Pump Discharge (M³) / Head(Mtr.) Location Latitude Longitude
1 VT Pump 280 LPM / 40 Mtr. Adori 27.658743 80.490233
OHT's
Sno. Structure Capacity (In KL) / Staging Ht.(Mtr.) Location Latitude Longitude
1 OHT 150 KL / 16 Mtr. Adori 27.658743 80.490233
Clear Water Rising Main
Sno. Pipe Type / Material Dia (In mm.) Length (In KM.) Remarks
1 D.I. Pipe 100 0.030
Distribution Network
Sno. Pipe Type / Material Dia (In mm.) Length (In KM.) Remarks
1 HDPE 63 2.771
2 HDPE 90 0.454
3 HDPE 110 0.796
HSC Connection
Sno. Total Nos.
1 238
Other Details
1.47
0.00
1.51
05-Apr-2024
14-Feb-2025