Project Completion Certificate (Ground Water)
Scheme ID: 20097723 Name of Scheme: KARIYAMAU & RAMPUR No. of Villages: 4 No. of Habitation Covered: 4
Total Population Covered: 5130 Base Year: 2023 Intermediate Year: 2038 Design Year: 2053
Date of Completion (As per Contract): 18-Mar-2025 Actual Date of Completion (Capex): 07-Mar-2025
Tubewells
Sno. Description Depth of Strainer (m) / Depth of Plain Pipe (m) Location Latitude Longitude
1 "Deep Tube well 450 LPM" 16.00 M / 139.35 M Kariyamau & Rampur 25.835995 81.021374
Pumps
Sno. Type of Pump Discharge (M³) / Head(Mtr.) Location Latitude Longitude
1 10.00 HP Submersible Pump 450 LPM / 60 M Kariyamau & Rampur 25.835995 81.021374
OHT's
Sno. Structure Capacity (In KL) / Staging Ht.(Mtr.) Location Latitude Longitude
1 Elevated Storage Reservoir 150 KL / 18 M Kariyamau & Rampur 25.836043 81.021245
Clear Water Rising Main
Sno. Pipe Type / Material Dia (In mm.) Length (In KM.) Remarks
Distribution Network
Sno. Pipe Type / Material Dia (In mm.) Length (In KM.) Remarks
1 HDPE PN-6 63 3.0589
2 HDPE PN-6 75 2.6167
3 HDPE PN-6 90 2.58
4 HDPE PN-6 110 2.6612
5 HDPE PN-6 125 0.7853
6 HDPE PN-6 140 0.361
7 HDPE PN-6 160 0.3399
8 HDPE PN-6 200 3.0124
HSC Connection
Sno. Total Nos.
1 884
Other Details
4.03
0.00
4.03
14-Jul-2025
15-Jul-2025