| Project Completion Certificate (Ground Water) | |||
|---|---|---|---|
| Scheme ID: 20097856 | Name of Scheme: SARAKPUR VILLAGE WATER SUPPLY SCHEME | No. of Villages: 1 | No. of Habitation Covered: 1 |
| Total Population Covered: 1080 | Base Year: 2022 | Intermediate Year: 2037 | Design Year: 2052 |
| Date of Completion (As per Contract): 07-Feb-2024 | Actual Date of Completion (Capex): 10-Jan-2025 | ||
| Tubewells | |||||
|---|---|---|---|---|---|
| Sno. | Description | Depth of Strainer (m) / Depth of Plain Pipe (m) | Location | Latitude | Longitude |
| 1 | TUBEWELL | 15M/135 | SARAKPUR | 28.376159 | 77.651043 |
| Pumps | |||||
|---|---|---|---|---|---|
| Sno. | Type of Pump | Discharge (M³) / Head(Mtr.) | Location | Latitude | Longitude |
| 1 | SUBMERSIBLE | 250LMP/55M | SARAKPUR | 28.376159 | 77.651043 |
| OHT's | |||||
|---|---|---|---|---|---|
| Sno. | Structure | Capacity (In KL) / Staging Ht.(Mtr.) | Location | Latitude | Longitude |
| 1 | OHT-01 | 75KL/12M | SARAKPUR | 28.376159 | 77.651043 |
| Clear Water Rising Main | ||||
|---|---|---|---|---|
| Sno. | Pipe Type / Material | Dia (In mm.) | Length (In KM.) | Remarks |
| 1 | DI PIPE | 80 | 0.017 | |
| Distribution Network | ||||
|---|---|---|---|---|
| Sno. | Pipe Type / Material | Dia (In mm.) | Length (In KM.) | Remarks |
| 1 | HDPE | 63 | 4.345 | |
| 2 | HDPE | 75 | 0.290 | |
| 3 | HDPE | 90 | 0.351 | |
| 4 | HDPE | 110 | 0.320 | |
| 5 | HDPE | 125 | 0.567 | |
| HSC Connection | |
|---|---|
| Sno. | Total Nos. |