| Project Completion Certificate (Ground Water) | |||
|---|---|---|---|
| Scheme ID: 20097907 | Name of Scheme: KALULI MAHBULLA PUR SVS | No. of Villages: 1 | No. of Habitation Covered: 1 |
| Total Population Covered: 1598 | Base Year: 2023 | Intermediate Year: 2038 | Design Year: 2053 |
| Date of Completion (As per Contract): 30-May-2025 | Actual Date of Completion (Capex): 17-May-2024 | ||
| Tubewells | |||||
|---|---|---|---|---|---|
| Sno. | Description | Depth of Strainer (m) / Depth of Plain Pipe (m) | Location | Latitude | Longitude |
| 1 | TUBEWELL | 15 M / 90.10 M | KALULI MAHBULLAPUR | 27.42691 | 79.44492 |
| Pumps | |||||
|---|---|---|---|---|---|
| Sno. | Type of Pump | Discharge (M³) / Head(Mtr.) | Location | Latitude | Longitude |
| 1 | SUBMERSIBLE | 300 LPM / 61 M | KALULI MAHBULLAPUR | 27.42691 | 79.44492 |
| OHT's | |||||
|---|---|---|---|---|---|
| Sno. | Structure | Capacity (In KL) / Staging Ht.(Mtr.) | Location | Latitude | Longitude |
| 1 | OHT | 75 KL / 14 M | KALULI MAHBULLAPUR | 27.42691 | 79.44492 |
| Clear Water Rising Main | ||||
|---|---|---|---|---|
| Sno. | Pipe Type / Material | Dia (In mm.) | Length (In KM.) | Remarks |
| 1 | DI / K7 | 100 | 27.5 | |
| Distribution Network | ||||
|---|---|---|---|---|
| Sno. | Pipe Type / Material | Dia (In mm.) | Length (In KM.) | Remarks |
| 1 | HDPE | 90 | .459 | |
| 2 | HDPE | 63 | 2.84 | |
| 3 | HDPE | 110 | .06 | |
| 4 | HDPE | 140 | .868 | |
| HSC Connection | |
|---|---|
| Sno. | Total Nos. |
| 1 | 314 |