| Project Completion Certificate (Ground Water) | |||
|---|---|---|---|
| Scheme ID: 20098069 | Name of Scheme: KANHAERI GP RO WSS | No. of Villages: 2 | No. of Habitation Covered: 2 |
| Total Population Covered: 3452 | Base Year: 2023 | Intermediate Year: 2038 | Design Year: 2053 |
| Date of Completion (As per Contract): 16-Sep-2022 | Actual Date of Completion (Capex): 14-Jan-2024 | ||
| Tubewells | |||||
|---|---|---|---|---|---|
| Sno. | Description | Depth of Strainer (m) / Depth of Plain Pipe (m) | Location | Latitude | Longitude |
| 1 | TUBEWELL | 24.05 M / 120.90 M | KANHAERI | 29.589245 | 77.517542 |
| Pumps | |||||
|---|---|---|---|---|---|
| Sno. | Type of Pump | Discharge (M³) / Head(Mtr.) | Location | Latitude | Longitude |
| 1 | SUBMERSIBLE | 690 LPM / 51 M | KANHAERI | 29.589245 | 77.517542 |
| OHT's | |||||
|---|---|---|---|---|---|
| Sno. | Structure | Capacity (In KL) / Staging Ht.(Mtr.) | Location | Latitude | Longitude |
| 1 | OHT | 125 KL / 12 M | KANHAERI | 29.589245 | 77.517542 |
| Clear Water Rising Main | ||||
|---|---|---|---|---|
| Sno. | Pipe Type / Material | Dia (In mm.) | Length (In KM.) | Remarks |
| 1 | D.I | 100 | 0.032 | |
| Distribution Network | ||||
|---|---|---|---|---|
| Sno. | Pipe Type / Material | Dia (In mm.) | Length (In KM.) | Remarks |
| 1 | HDPE | 90 | 0.31065 | |
| 2 | HDPE | 75 | 0.82349 | |
| 3 | HDPE | 63 | 7.31011 | |
| 4 | HDPE | 110 | 1.24045 | |
| 5 | HDPE | 125 | 0.2514 | |
| 6 | HDPE | 140 | 0.03401 | |
| 7 | HDPE | 160 | 0.17287 | |
| 8 | HDPE | 180 | 0.03254 | |
| HSC Connection | |
|---|---|
| Sno. | Total Nos. |
| 1 | 740 |