Project Completion Certificate (Ground Water)
Scheme ID: 20098092 Name of Scheme: SOWNAHWA & HARIHARPUR WATER SUPPLY SCHEME No. of Villages: 1 No. of Habitation Covered: 1
Total Population Covered: 2050 Base Year: 2022 Intermediate Year: 2037 Design Year: 2052
Date of Completion (As per Contract): 31-Dec-2026 Actual Date of Completion (Capex): 06-Sep-2025
Tubewells
Sno. Description Depth of Strainer (m) / Depth of Plain Pipe (m) Location Latitude Longitude
1 Tubewell 21.09/158.36 Sonahawa 27.57338 82.70048
Pumps
Sno. Type of Pump Discharge (M³) / Head(Mtr.) Location Latitude Longitude
1 VT Pump -1 350 LPM Discharge/ 43 mtr Head Sonahawa 27.57338 82.70048
OHT's
Sno. Structure Capacity (In KL) / Staging Ht.(Mtr.) Location Latitude Longitude
1 OHT-1 100 KL/16 Mtr Sonahawa 27.57338 82.70048
Clear Water Rising Main
Sno. Pipe Type / Material Dia (In mm.) Length (In KM.) Remarks
1 DI, K-7 100 100
Distribution Network
Sno. Pipe Type / Material Dia (In mm.) Length (In KM.) Remarks
1 140 mm dia HDPE Pipe PN 6: Class PE 100 140 0.03000
2 110 mm dia HDPE Pipe PN 6: Class PE 100 110 0.013
3 90 mm dia HDPE Pipe PN 6: Class PE 100 90 1.669
4 75 mm dia HDPE Pipe PN 6: Class PE 100 75 2.204
5 63 mm dia HDPE Pipe PN 6: Class PE 100 63 3.413
HSC Connection
Sno. Total Nos.
Other Details
1.57
0.00
1.89
06-Dec-2025
06-Dec-2025