Project Completion Certificate (Ground Water)
Scheme ID: 20098109 Name of Scheme: UPLEHRA No. of Villages: 1 No. of Habitation Covered: 1
Total Population Covered: 1990 Base Year: 2023 Intermediate Year: 2038 Design Year: 2053
Date of Completion (As per Contract): 31-Dec-2024 Actual Date of Completion (Capex): 23-Jan-2024
Tubewells
Sno. Description Depth of Strainer (m) / Depth of Plain Pipe (m) Location Latitude Longitude
1 Tubewell 22.21 Mtr / 103.12 Mtr UPLEHRA 28.916184 77.624634
Pumps
Sno. Type of Pump Discharge (M³) / Head(Mtr.) Location Latitude Longitude
1 Submersible 200 LPM / 50 Mtr UPLEHRA 28.916184 77.624634
OHT's
Sno. Structure Capacity (In KL) / Staging Ht.(Mtr.) Location Latitude Longitude
1 OHT 75 Kl / 14 M UPLEHRA 28.916184 77.624634
Clear Water Rising Main
Sno. Pipe Type / Material Dia (In mm.) Length (In KM.) Remarks
1 DI 100 0.0208
Distribution Network
Sno. Pipe Type / Material Dia (In mm.) Length (In KM.) Remarks
1 HDPE 63 2.3076
2 HDPE 90 1.1221
3 HDPE 110 0.386
4 HDPE 125 0.1433
5 HDPE 140 0.564
HSC Connection
Sno. Total Nos.
1 384
Other Details
1.79
1.79
1.46
10-Jun-2024
07-Nov-2024