Project Completion Certificate (Ground Water)
Scheme ID: 20098293 Name of Scheme: SADIPUR WATER SUPPLY SCHEME No. of Villages: 1 No. of Habitation Covered: 3
Total Population Covered: 2882 Base Year: 2022 Intermediate Year: 2037 Design Year: 2052
Date of Completion (As per Contract): 27-May-2025 Actual Date of Completion (Capex): 07-Sep-2024
Tubewells
Sno. Description Depth of Strainer (m) / Depth of Plain Pipe (m) Location Latitude Longitude
1 150MM PLAIN PIPE 6 SADIPUR 26.441645 81.753236
2 300MM PLAIN PIPE 74 SADIPUR 26.441645 81.753236
3 150MM SLOTTED PIPE 17 SADIPUR 26.441645 81.753236
Pumps
Sno. Type of Pump Discharge (M³) / Head(Mtr.) Location Latitude Longitude
1 SUBMERSIBLE PUMP 610LPM / 54MTR SADIPUR 26.441645 81.753236
OHT's
Sno. Structure Capacity (In KL) / Staging Ht.(Mtr.) Location Latitude Longitude
1 OVER HEAD TANK 400KL / 17MTR SADIPUR 26.441645 81.753236
Clear Water Rising Main
Sno. Pipe Type / Material Dia (In mm.) Length (In KM.) Remarks
1 DI PIPE 100 28.70
Distribution Network
Sno. Pipe Type / Material Dia (In mm.) Length (In KM.) Remarks
1 HDPE PIPE 90 .709
2 HDPE PIPE 63 6.65
3 HDPE PIPE 110 .120
4 HDPE PIPE 140 .446
5 HDPE PIPE 160 1.38
6 HDPE PIPE 180 .057
HSC Connection
Sno. Total Nos.
1 498
Other Details
2.77
0.00
2.70
13-Dec-2024
15-Mar-2025