| Project Completion Certificate (Ground Water) | |||
|---|---|---|---|
| Scheme ID: 20098321 | Name of Scheme: PURE MIHIB SHAH Water Supply Scheme | No. of Villages: 2 | No. of Habitation Covered: 7 |
| Total Population Covered: 3000 | Base Year: 2023 | Intermediate Year: 2038 | Design Year: 2053 |
| Date of Completion (As per Contract): 04-Jul-2024 | Actual Date of Completion (Capex): 05-Jun-2024 | ||
| Tubewells | |||||
|---|---|---|---|---|---|
| Sno. | Description | Depth of Strainer (m) / Depth of Plain Pipe (m) | Location | Latitude | Longitude |
| 1 | TUBEWELL | 17.02 M / 53.73 M | PURE MIHIB SHAH | 28.935158 | 77.916346 |
| Pumps | |||||
|---|---|---|---|---|---|
| Sno. | Type of Pump | Discharge (M³) / Head(Mtr.) | Location | Latitude | Longitude |
| 1 | SUBMERSIBLE | 650 M / 52 M | PURE MIHIB SHAH | 28.935158 | 77.916346 |
| OHT's | |||||
|---|---|---|---|---|---|
| Sno. | Structure | Capacity (In KL) / Staging Ht.(Mtr.) | Location | Latitude | Longitude |
| 1 | OHT | 200 KL / 14 M | PURE MIHIB SHAH | 28.935158 | 77.916346 |
| Clear Water Rising Main | ||||
|---|---|---|---|---|
| Sno. | Pipe Type / Material | Dia (In mm.) | Length (In KM.) | Remarks |
| 1 | DI | 100 | 0.018 | |
| Distribution Network | ||||
|---|---|---|---|---|
| Sno. | Pipe Type / Material | Dia (In mm.) | Length (In KM.) | Remarks |
| 1 | HDPE | 63 | 7.785 | |
| 2 | HDPE | 90 | 1.099 | |
| 3 | HDPE | 110 | 1.140 | |
| 4 | HDPE | 140 | 1.963 | |
| 5 | HDPE | 160 | 0.024 | |
| 6 | HDPE | 180 | 0.532 | |
| HSC Connection | |
|---|---|
| Sno. | Total Nos. |
| 1 | 580 |