Project Completion Certificate (Ground Water)
Scheme ID: 20098338 Name of Scheme: PURAB DWARA Water Supply Scheme No. of Villages: 1 No. of Habitation Covered: 3
Total Population Covered: 1541 Base Year: 2023 Intermediate Year: 2038 Design Year: 2053
Date of Completion (As per Contract): 04-Jul-2024 Actual Date of Completion (Capex): 11-Nov-2024
Tubewells
Sno. Description Depth of Strainer (m) / Depth of Plain Pipe (m) Location Latitude Longitude
1 TUBEWELL 18.32 M /70.53 PURAB DWARA 28.909112 77.901689
Pumps
Sno. Type of Pump Discharge (M³) / Head(Mtr.) Location Latitude Longitude
1 SUBMERSIBLE 650 LPM / 52 M PURAB DWARA 28.909112 77.901689
OHT's
Sno. Structure Capacity (In KL) / Staging Ht.(Mtr.) Location Latitude Longitude
1 OHT 50 KL /14 M PURAB DWARA 28.909112 77.901689
Clear Water Rising Main
Sno. Pipe Type / Material Dia (In mm.) Length (In KM.) Remarks
1 DI 100 0.025
Distribution Network
Sno. Pipe Type / Material Dia (In mm.) Length (In KM.) Remarks
1 HDPE 63 7.516
2 HDPE 90 4.075
3 HDPE 110 0.200
4 HDPE 140 0.420
HSC Connection
Sno. Total Nos.
1 284
Other Details
1.90
0.00
1.91
11-Feb-2025
10-May-2025