Project Completion Certificate (Ground Water)
Scheme ID: 20098368 Name of Scheme: Kabdaut & Butrari Water Supply Scheme Reorganisation No. of Villages: 2 No. of Habitation Covered: 2
Total Population Covered: 6529 Base Year: 2022 Intermediate Year: 2037 Design Year: 2052
Date of Completion (As per Contract): 15-Jun-2024 Actual Date of Completion (Capex): 19-Nov-2024
Tubewells
Sno. Description Depth of Strainer (m) / Depth of Plain Pipe (m) Location Latitude Longitude
1 200 mm 300 mtr plain pipe oht campus 29.402834 77.348202
2 200 mm 137.17 mtr slotted pipe oht campus 29.402834 77.348202
Pumps
Sno. Type of Pump Discharge (M³) / Head(Mtr.) Location Latitude Longitude
1 12.5 hp 450 LPM/ 55mtr oht campus 29.402834 77.348202
2 12.5 hp 450 LPM/ 55mtr oht campus 29.402834 77.348202
OHT's
Sno. Structure Capacity (In KL) / Staging Ht.(Mtr.) Location Latitude Longitude
1 ( existing oht 100 kl/ 14 mtr oht campus 29.402834 77.348202
2 new concrete oht 200 kl/ 14 mtr new oht campus 29.402834 77.348202
Clear Water Rising Main
Sno. Pipe Type / Material Dia (In mm.) Length (In KM.) Remarks
1 di k7 125 0.003 new oht
2 di k7 100 0.016 old oht
Distribution Network
Sno. Pipe Type / Material Dia (In mm.) Length (In KM.) Remarks
1 hdpe 90 1.2442
2 HDPE 75 0.5269
3 HDPE 63 8.8626
4 HDPE 110 0.628
5 HDPE 140 0.6854
6 HDPE 160 0.3951
7 HDPE 180 0.1761
HSC Connection
Sno. Total Nos.
1 1485
Other Details
60343000.00
57902000.00
52909806.00
19-Nov-2024
01-Mar-2026