Project Completion Certificate (Ground Water)
Scheme ID: 20098525 Name of Scheme: Haibatpur Dubhawon Water Supply Scheme (Re-Organization) No. of Villages: 4 No. of Habitation Covered: 10
Total Population Covered: 5671 Base Year: 2023 Intermediate Year: 2038 Design Year: 2053
Date of Completion (As per Contract): 24-Sep-2024 Actual Date of Completion (Capex): 27-Oct-2024
Tubewells
Sno. Description Depth of Strainer (m) / Depth of Plain Pipe (m) Location Latitude Longitude
1 Tubewell 27/74.3 Haibatpur Dubhawon 25.76223 83.13851
Pumps
Sno. Type of Pump Discharge (M³) / Head(Mtr.) Location Latitude Longitude
1 Submersible Pump 900/48 Haibatpur Dubhawon 25.76223 83.13851
OHT's
Sno. Structure Capacity (In KL) / Staging Ht.(Mtr.) Location Latitude Longitude
1 OHT-1 250/14 Haibatpur Dubhawon 25.76223 83.13851
Clear Water Rising Main
Sno. Pipe Type / Material Dia (In mm.) Length (In KM.) Remarks
1 K-7/DI PIPE 150 0.04
Distribution Network
Sno. Pipe Type / Material Dia (In mm.) Length (In KM.) Remarks
1 HDPE Pipe PN-6: Class PE-100 63 23.170
2 HDPE Pipe PN-6: Class PE-100 75 1.550
3 HDPE Pipe PN-6: Class PE-100 90 1.270
4 HDPE Pipe PN-6: Class PE-100 110 0.890
5 HDPE Pipe PN-6: Class PE-100 140 0.430
6 HDPE Pipe PN-6: Class PE-100 180 0.190
HSC Connection
Sno. Total Nos.
1 662
Other Details
3.30
3.30
2.75
30-Jan-2025
31-Jan-2025