Project Completion Certificate (Ground Water)
Scheme ID: 20099288 Name of Scheme: Damarpur PWS No. of Villages: 1 No. of Habitation Covered: 1
Total Population Covered: 3024 Base Year: 2023 Intermediate Year: 2038 Design Year: 2053
Date of Completion (As per Contract): 06-Jan-2022 Actual Date of Completion (Capex): 08-Sep-2023
Tubewells
Sno. Description Depth of Strainer (m) / Depth of Plain Pipe (m) Location Latitude Longitude
Pumps
Sno. Type of Pump Discharge (M³) / Head(Mtr.) Location Latitude Longitude
OHT's
Sno. Structure Capacity (In KL) / Staging Ht.(Mtr.) Location Latitude Longitude
Clear Water Rising Main
Sno. Pipe Type / Material Dia (In mm.) Length (In KM.) Remarks
Distribution Network
Sno. Pipe Type / Material Dia (In mm.) Length (In KM.) Remarks
1 HDPE 63 .717
2 HDPE 90 .838
HSC Connection
Sno. Total Nos.
Other Details
0.80
0.00
0.81
18-Jul-2024
20-Jul-2024