| Project Completion Certificate (Ground Water) | |||
|---|---|---|---|
| Scheme ID: 20099387 | Name of Scheme: VATIYA WATER SUPPLY SCHEME | No. of Villages: 1 | No. of Habitation Covered: 1 |
| Total Population Covered: 2173 | Base Year: 2022 | Intermediate Year: 2037 | Design Year: 2052 |
| Date of Completion (As per Contract): 27-Nov-2024 | Actual Date of Completion (Capex): 07-Jun-2024 | ||
| Tubewells | |||||
|---|---|---|---|---|---|
| Sno. | Description | Depth of Strainer (m) / Depth of Plain Pipe (m) | Location | Latitude | Longitude |
| 1 | PLAIN PIPE 200MM | 54.50 | VATIYA | 26.487961 | 81.506803 |
| 2 | SLOTTED PIPE 200MMM | 18 | VATIYA | 26.487961 | 81.506803 |
| 3 | PLAIN PIPE 150MM | 45 | VATIYA | 26.487961 | 81.506803 |
| 4 | SLOTTED PIPE 150MMM | 3 | VATIYA | 26.487961 | 81.506803 |
| Pumps | |||||
|---|---|---|---|---|---|
| Sno. | Type of Pump | Discharge (M³) / Head(Mtr.) | Location | Latitude | Longitude |
| 1 | SUBMERSIBLE PUMP | 500LPM | VATIYA | 26.487961 | 81.506803 |
| OHT's | |||||
|---|---|---|---|---|---|
| Sno. | Structure | Capacity (In KL) / Staging Ht.(Mtr.) | Location | Latitude | Longitude |
| 1 | OVER HEAD TANK | 125KL/14MTR | VATIYA | 26.487961 | 81.506803 |
| Clear Water Rising Main | ||||
|---|---|---|---|---|
| Sno. | Pipe Type / Material | Dia (In mm.) | Length (In KM.) | Remarks |
| 1 | DI PIPE | 100 | 0.023 | |
| Distribution Network | ||||
|---|---|---|---|---|
| Sno. | Pipe Type / Material | Dia (In mm.) | Length (In KM.) | Remarks |
| 1 | HDPE PIPE | 90 | 0.292 | |
| 2 | HDPE PIPE | 75 | .266 | |
| 3 | HDPE PIPE | 63 | 3.728 | |
| 4 | HDPE PIPE | 110 | .637 | |
| 5 | HDPE PIPE | 125 | .267 | |
| 6 | HDPE PIPE | 160 | 1.023 | |
| 7 | HDPE PIPE | 180 | .183 | |
| HSC Connection | |
|---|---|
| Sno. | Total Nos. |
| 1 | 346 |