Project Completion Certificate (Ground Water)
Scheme ID: 20099387 Name of Scheme: VATIYA WATER SUPPLY SCHEME No. of Villages: 1 No. of Habitation Covered: 1
Total Population Covered: 2173 Base Year: 2022 Intermediate Year: 2037 Design Year: 2052
Date of Completion (As per Contract): 27-Nov-2024 Actual Date of Completion (Capex): 07-Jun-2024
Tubewells
Sno. Description Depth of Strainer (m) / Depth of Plain Pipe (m) Location Latitude Longitude
1 PLAIN PIPE 200MM 54.50 VATIYA 26.487961 81.506803
2 SLOTTED PIPE 200MMM 18 VATIYA 26.487961 81.506803
3 PLAIN PIPE 150MM 45 VATIYA 26.487961 81.506803
4 SLOTTED PIPE 150MMM 3 VATIYA 26.487961 81.506803
Pumps
Sno. Type of Pump Discharge (M³) / Head(Mtr.) Location Latitude Longitude
1 SUBMERSIBLE PUMP 500LPM VATIYA 26.487961 81.506803
OHT's
Sno. Structure Capacity (In KL) / Staging Ht.(Mtr.) Location Latitude Longitude
1 OVER HEAD TANK 125KL/14MTR VATIYA 26.487961 81.506803
Clear Water Rising Main
Sno. Pipe Type / Material Dia (In mm.) Length (In KM.) Remarks
1 DI PIPE 100 0.023
Distribution Network
Sno. Pipe Type / Material Dia (In mm.) Length (In KM.) Remarks
1 HDPE PIPE 90 0.292
2 HDPE PIPE 75 .266
3 HDPE PIPE 63 3.728
4 HDPE PIPE 110 .637
5 HDPE PIPE 125 .267
6 HDPE PIPE 160 1.023
7 HDPE PIPE 180 .183
HSC Connection
Sno. Total Nos.
1 346
Other Details
2.22
0.00
2.20
11-Sep-2024
15-Jan-2025