Project Completion Certificate (Ground Water)
Scheme ID: 20099435 Name of Scheme: PAHARPUR No. of Villages: 2 No. of Habitation Covered: 3
Total Population Covered: 2670 Base Year: 2023 Intermediate Year: 2038 Design Year: 2053
Date of Completion (As per Contract): 13-Aug-2024 Actual Date of Completion (Capex): 30-Jun-2025
Tubewells
Sno. Description Depth of Strainer (m) / Depth of Plain Pipe (m) Location Latitude Longitude
1 Tube well 10/54.54 PAHARPUR 25.6472523" 80.9843166"
Pumps
Sno. Type of Pump Discharge (M³) / Head(Mtr.) Location Latitude Longitude
1 Submersible 540/60 PAHARPUR 25.6472523" 80.9843166"
OHT's
Sno. Structure Capacity (In KL) / Staging Ht.(Mtr.) Location Latitude Longitude
1 OHT-1 175/16 PAHARPUR 25.6472523" 80.9843166"
Clear Water Rising Main
Sno. Pipe Type / Material Dia (In mm.) Length (In KM.) Remarks
1 D.I. K,9 100 0.018
Distribution Network
Sno. Pipe Type / Material Dia (In mm.) Length (In KM.) Remarks
1 HDPE 200 0.2181
2 HDPE 140 0.1243
3 HDPE 125 0.4757
4 HDPE 110 2.2832
5 HDPE 90 0.7824
6 HDPE 75 2.1762
7 HDPE 63 6.2441
HSC Connection
Sno. Total Nos.
1 440
Other Details
2.18
0.00
2.23
18-Apr-2025
19-Apr-2025