| Project Completion Certificate (Ground Water) | |||
|---|---|---|---|
| Scheme ID: 20099522 | Name of Scheme: Khadaniya Water Supply Scheme | No. of Villages: 1 | No. of Habitation Covered: 2 |
| Total Population Covered: 2465 | Base Year: 2022 | Intermediate Year: 2037 | Design Year: 2052 |
| Date of Completion (As per Contract): 07-Jan-2023 | Actual Date of Completion (Capex): 25-Dec-2023 | ||
| Tubewells | |||||
|---|---|---|---|---|---|
| Sno. | Description | Depth of Strainer (m) / Depth of Plain Pipe (m) | Location | Latitude | Longitude |
| 1 | Tubewell | 23 / 123.90 | Khandaniya | 27.604374 | 80.784084 |
| Pumps | |||||
|---|---|---|---|---|---|
| Sno. | Type of Pump | Discharge (M³) / Head(Mtr.) | Location | Latitude | Longitude |
| 1 | VT Pump | 540 LPM / 43 Mtr. | Khandaniya | 27.604374 | 80.784084 |
| OHT's | |||||
|---|---|---|---|---|---|
| Sno. | Structure | Capacity (In KL) / Staging Ht.(Mtr.) | Location | Latitude | Longitude |
| 1 | OHT | 150 KL / 12 Mtr. | Khandaniya | 27.604374 | 80.784084 |
| Clear Water Rising Main | ||||
|---|---|---|---|---|
| Sno. | Pipe Type / Material | Dia (In mm.) | Length (In KM.) | Remarks |
| 1 | D.I. Pipe | 100 | 0.025 | |
| Distribution Network | ||||
|---|---|---|---|---|
| Sno. | Pipe Type / Material | Dia (In mm.) | Length (In KM.) | Remarks |
| 1 | HDPE | 63 | 4.449 | |
| 2 | HDPE | 75 | 0.087 | |
| 3 | HDPE | 90 | 0.261 | |
| 4 | HDPE | 110 | 0.916 | |
| 5 | HDPE | 140 | 1.195 | |
| 6 | HDPE | 160 | 0.080 | |
| HSC Connection | |
|---|---|
| Sno. | Total Nos. |
| 1 | 420 |