| Project Completion Certificate (Ground Water) | |||
|---|---|---|---|
| Scheme ID: 20099637 | Name of Scheme: JALALPUR KALA & JALILPUR MVS (O) | No. of Villages: 3 | No. of Habitation Covered: 3 |
| Total Population Covered: 2821 | Base Year: 2023 | Intermediate Year: 2038 | Design Year: 2053 |
| Date of Completion (As per Contract): 31-Dec-2024 | Actual Date of Completion (Capex): 18-Jan-2025 | ||
| Tubewells | |||||
|---|---|---|---|---|---|
| Sno. | Description | Depth of Strainer (m) / Depth of Plain Pipe (m) | Location | Latitude | Longitude |
| 1 | Tubewell | 18.06/90.54 | Jalalpur kalan | 28.8533 | 78.3386 |
| Pumps | |||||
|---|---|---|---|---|---|
| Sno. | Type of Pump | Discharge (M³) / Head(Mtr.) | Location | Latitude | Longitude |
| 1 | Solar Powered Pump | 560/40 | Jalalpur kalan | 28.8533 | 78.3386 |
| OHT's | |||||
|---|---|---|---|---|---|
| Sno. | Structure | Capacity (In KL) / Staging Ht.(Mtr.) | Location | Latitude | Longitude |
| 1 | Cast in situ Zinc Zincalume | 175/12 | Jalalpur kalan | 28.8532 | 78.3385 |
| Clear Water Rising Main | ||||
|---|---|---|---|---|
| Sno. | Pipe Type / Material | Dia (In mm.) | Length (In KM.) | Remarks |
| 1 | K-7/DI | 125 | 0.02113 | |
| Distribution Network | ||||
|---|---|---|---|---|
| Sno. | Pipe Type / Material | Dia (In mm.) | Length (In KM.) | Remarks |
| 1 | PN-6 PE100/HDPE | 90 | 0.040 | |
| 2 | PN-6 PE100/HDPE | 75 | 0.147 | |
| 3 | PN-6 PE100/HDPE | 63 | 7.3627 | |
| 4 | PN-6 PE100/HDPE | 110 | 0.208 | |
| 5 | PN-6 PE100/HDPE | 125 | 0.059 | |
| 6 | PN-6 PE100/HDPE | 140 | 1.430 | |
| 7 | PN-6 PE100/HDPE | 160 | 0.074 | |
| HSC Connection | |
|---|---|
| Sno. | Total Nos. |
| 1 | 459 |