| Project Completion Certificate (Ground Water) | |||
|---|---|---|---|
| Scheme ID: 20099821 | Name of Scheme: Kaidaha Khurd Water Supply Scheme | No. of Villages: 2 | No. of Habitation Covered: 2 |
| Total Population Covered: 1480 | Base Year: 2022 | Intermediate Year: 2037 | Design Year: 2052 |
| Date of Completion (As per Contract): 23-Feb-2025 | Actual Date of Completion (Capex): 11-May-2025 | ||
| Tubewells | |||||
|---|---|---|---|---|---|
| Sno. | Description | Depth of Strainer (m) / Depth of Plain Pipe (m) | Location | Latitude | Longitude |
| 1 | Tubewell | 15.00/123.85 | Kaidaha Khurd | 26.486557 | 83.427519 |
| Pumps | |||||
|---|---|---|---|---|---|
| Sno. | Type of Pump | Discharge (M³) / Head(Mtr.) | Location | Latitude | Longitude |
| 1 | Submersible Pump | 21/41 | Kaidaha Khurd | 26.486564 | 83.42793 |
| OHT's | |||||
|---|---|---|---|---|---|
| Sno. | Structure | Capacity (In KL) / Staging Ht.(Mtr.) | Location | Latitude | Longitude |
| 1 | Over Head Tank-1 | 75/14 | Kaidaha Khurd | 26.48661 | 83.42748 |
| Clear Water Rising Main | ||||
|---|---|---|---|---|
| Sno. | Pipe Type / Material | Dia (In mm.) | Length (In KM.) | Remarks |
| 1 | DI | 100 | 0.030 | Completed |
| Distribution Network | ||||
|---|---|---|---|---|
| Sno. | Pipe Type / Material | Dia (In mm.) | Length (In KM.) | Remarks |
| 1 | HDPE | 63 | 6.436 | Completed |
| 2 | HDPE | 90 | 0.728 | Completed |
| HSC Connection | |
|---|---|
| Sno. | Total Nos. |
| 1 | 254 |