Project Completion Certificate (Ground Water)
Scheme ID: 20100806 Name of Scheme: GHANGHAOL No. of Villages: 1 No. of Habitation Covered: 1
Total Population Covered: 3970 Base Year: 2023 Intermediate Year: 2038 Design Year: 2053
Date of Completion (As per Contract): 20-Sep-2024 Actual Date of Completion (Capex): 19-Feb-2025
Tubewells
Sno. Description Depth of Strainer (m) / Depth of Plain Pipe (m) Location Latitude Longitude
1 Deep Tube well 800 LPM 20 / 121.12 Ghanghaol 25.806058 80.842440
Pumps
Sno. Type of Pump Discharge (M³) / Head(Mtr.) Location Latitude Longitude
1 20 HP Submersible Pump 800 / 55 Ghanghaol 25.806058 80.842440
OHT's
Sno. Structure Capacity (In KL) / Staging Ht.(Mtr.) Location Latitude Longitude
1 Elevated Storage Reservoir 250 KL / 12 M Ghanghaol 25.806653 80.842573
Clear Water Rising Main
Sno. Pipe Type / Material Dia (In mm.) Length (In KM.) Remarks
1 DI K-9 150 0.014
Distribution Network
Sno. Pipe Type / Material Dia (In mm.) Length (In KM.) Remarks
1 HDPE PN-6 PE 100 200 0.0293
2 HDPE PN-6 PE-100 180 0.298
3 HDPE PN-6 PE 100 160 0.109
4 HDPE PN-6 PE 100 140 0.078
5 HDPE PN-6 PE 100 125 0.466
6 HDPE PN-6 PE 100 110 0.0705
7 HDPE PN-6 PE 100 90 0.536
8 HDPE PN-6 PE 100 75 1.3717
9 HDPE PN-6 PE 100 63 3.77738
HSC Connection
Sno. Total Nos.
1 573
Other Details
2.82
0.00
2.80
19-Feb-2025
20-Feb-2025