| Project Completion Certificate (Ground Water) | |||
|---|---|---|---|
| Scheme ID: 20100852 | Name of Scheme: BHARAT BANGAR GRAM PANCHAYAT WATER SUPPLY SCHEME | No. of Villages: 2 | No. of Habitation Covered: 4 |
| Total Population Covered: 2746 | Base Year: 2023 | Intermediate Year: 2038 | Design Year: 2053 |
| Date of Completion (As per Contract): 12-Feb-2024 | Actual Date of Completion (Capex): 12-Aug-2025 | ||
| Tubewells | |||||
|---|---|---|---|---|---|
| Sno. | Description | Depth of Strainer (m) / Depth of Plain Pipe (m) | Location | Latitude | Longitude |
| 1 | Tubewell | 21 M/311.54 M | BHARAT BANGAR | 26.579072 | 80.251845 |
| Pumps | |||||
|---|---|---|---|---|---|
| Sno. | Type of Pump | Discharge (M³) / Head(Mtr.) | Location | Latitude | Longitude |
| 1 | VT Pump-1 | 544 LPM/57 M | BHARAT BANGAR | 26.579072 | 80.251845 |
| OHT's | |||||
|---|---|---|---|---|---|
| Sno. | Structure | Capacity (In KL) / Staging Ht.(Mtr.) | Location | Latitude | Longitude |
| 1 | OHT-1 | 175 KL/12 M (ZINC ALAM TANK) | BHARAT BANGAR | 26.579072 | 80.251845 |
| Clear Water Rising Main | ||||
|---|---|---|---|---|
| Sno. | Pipe Type / Material | Dia (In mm.) | Length (In KM.) | Remarks |
| 1 | DI/K-7 | 150 | 0.017 | |
| Distribution Network | ||||
|---|---|---|---|---|
| Sno. | Pipe Type / Material | Dia (In mm.) | Length (In KM.) | Remarks |
| 1 | HDPE/PN-6 | 63 | 5.685 | |
| 2 | HDPE/PN-6 | 75 | 0.823 | |
| 3 | HDPE/PN-6 | 90 | 0.9665 | |
| 4 | HDPE/PN-6 | 110 | 0.481 | |
| 5 | HDPE/PN-6 | 140 | 0.975 | |
| 6 | HDPE/PN-6 | 160 | 0.064 | |
| HSC Connection | |
|---|---|
| Sno. | Total Nos. |
| 1 | 570 |