Project Completion Certificate (Ground Water)
Scheme ID: 20100876 Name of Scheme: MUSEPUR GRAM PANCHAYAT WATER SUPPLY SCHEME No. of Villages: 2 No. of Habitation Covered: 2
Total Population Covered: 1796 Base Year: 2023 Intermediate Year: 2038 Design Year: 2053
Date of Completion (As per Contract): 26-May-2023 Actual Date of Completion (Capex): 26-Nov-2024
Tubewells
Sno. Description Depth of Strainer (m) / Depth of Plain Pipe (m) Location Latitude Longitude
1 Tubewell 24 M/123.50 M MUSEPUR 26.277036 80.097761
Pumps
Sno. Type of Pump Discharge (M³) / Head(Mtr.) Location Latitude Longitude
1 VT Pump-1 369 LPM/62 M MUSEPUR 26.277036 80.097761
OHT's
Sno. Structure Capacity (In KL) / Staging Ht.(Mtr.) Location Latitude Longitude
1 OHT-1 100 KL/12 M (ZINC ALAM TANK) MUSEPUR 26.277036 80.097761
Clear Water Rising Main
Sno. Pipe Type / Material Dia (In mm.) Length (In KM.) Remarks
1 DI/K-7 100 0.020
Distribution Network
Sno. Pipe Type / Material Dia (In mm.) Length (In KM.) Remarks
1 HDPE/PN-6 63 3.087
2 HDPE/PN-6 75 0.523
3 HDPE/PN-6 90 0.068
4 HDPE/PN-6 110 1.056
5 HDPE/PN-6 140 0.208
6 HDPE/PN-6 160 0.108
HSC Connection
Sno. Total Nos.
1 352
Other Details
1.56
0.00
0.00
14-Jan-2025
15-Jan-2025